IVM Eeklo Belgium: Boiler and Furnace Upgrades

Babcock & Wilcox are sponsors of Operational Optimisation. EfW Network members can get discounted tickets. See the code below and book now.
IVM Eeklo Belgium: Boiler and Furnace Upgrades
Like

Share this post

Choose a social network to share with, or copy the URL to share elsewhere

This is a representation of how your post may appear on social media. The actual post will vary between social networks

Project description


Babcock & Wilcox Renewable Service won the order of an extensive upgrade project for two identical waste-to-energy lines in Eeklo, Belgium. The scope included engineering, manufacturing, delivery, construction advisory services, commissioning, testing, operator training, and project management for new feeding systems, grates, riddlings and slag handling systems, water-cooled furnaces, combustion air system, support burners and hydraulic system.Computational fluid dynamic (CFD) models were utilized to determine new furnace geometry, secondary air nozzle and burner locations, and to predict the temperature distribution.

Scope of delivery

Feeding system
Waste feeding hopper, hydraulically operated feed damper, watercooled chute, feeding pusher, and casing around the grate and boiler. 


Combustion grate
Air-cooled hydraulically driven DynaGrate® combustion grate, 2.8 m 
wide and 9.9 m long.


Siftings and slag system

Four air zones and sifting hoppers under the grate with a common 
submerged conveyor underneath the set of sifting hoppers and slag 
chute. The submerged conveyor, which is based on wet operation, 
feeds the siftings into an open container in an outside container hall. 

Start-up burners
Two 12.5 MW start-up/support burners for natural gas including local instruments, valves and PLC.


Combustion air system
Basic design of primary, secondary and cooling air 
systems.

Water-cooled furnace
Water-cooled furnace constructed of panel walls and wear zones. Furnace walls use Inconel® cladding with the exception of front and rear roofs. Six riser pipes from new furnace connected to existing steam drum. Supply pipes for new furnace connected to existing downcomer pipes.
Furnace walls were pressure tested and Inconel cladded in workshop before delivery to site.


Galleries, platforms and support steel
Basic design of galleries, platforms and support structural steel for B&W Renewable supplied 
equipment.

Valves
Complete valve package.


Hydraulic system
Complete hydraulic system for grate, feeding pusher and damper in feeding chute including local 
instruments, valves and pipes and spill protection bin.

Results 

An extended asset life is anticipated from these results:
• Safer and easier daily maintenance
• More stable combustion process
• More stable steam production
• Up to 12.5% higher energy recovery 
• Greater electricity production
• Better permit compliance
• 35% less fly ash 
• Longer run time between outage